National Grid ESO Implements Reforms to Accelerate Electricity Network Connections

System Operator (ESO) is taking further measures to expedite connections to the electricity network. In a recent communication, the ESO has reached out to parties seeking to connect to the transmission system, requesting updates on their progress and project milestones. This proactive approach aims to identify non-viable developments, thereby enabling prompt connections for projects that are ready and capable of joining the grid.

This initiative follows a decision by the Code Panel, the regulatory body responsible for implementing changes to the codes governing the energy industry. The Code Panel has recommended modifications to connection contracts management to enhance the ESO's ability to effectively manage the connection queue.

Under the proposed changes, energy generators that are not making sufficient progress and are unlikely to meet their connection date will have the option to either step back in the queue or withdraw altogether. This will create opportunities for projects that are keen to connect and are successfully meeting their milestones. Consequently, these reforms have the potential to enable developments to connect up to a decade earlier than previously possible.

The milestones that projects must achieve include crucial points such as securing financing, acquiring land, obtaining planning permission, and commencing construction. It is important to note that projects facing delays due to network build issues beyond the control of developers will not be adversely affected by these reforms.

To ensure the progress of projects towards their contracted connection dates, the ESO will be supported by an international engineering consultancy and a legal firm, which will assist in the verification and assessment process.

Additionally, the ESO is expressing its support for changes that would allow developers to construct their own connections to the grid. This move has garnered praise from groups as it is seen as a means of resolving the backlog currently impeding progress on projects.

Barnaby Wharton, the director of future electricity systems at , hailed the announcement as a significant step forward in accelerating the deployment of clean energy capacity. He explained that these reforms would prioritize projects that are ready to connect, rather than allowing inactive or unprepared schemes to obstruct progress. Wharton believes that by avoiding the accumulation of speculative bids in the connection queue, the reforms will enable projects that are prepared to go live to move ahead.

Stephen McKellar, senior policy manager at , emphasized the importance of fast-tracking renewable energy generation projects' connection to the electricity network as a key component in achieving the goal of net zero emissions. He welcomed any measures that expedite this process. McKellar further stated that Scottish Renewables has long advocated for a fair and proportionate approach to managing the growing number of projects in the connection queue. However, he stressed the significance of making decisions regarding the relocation or removal of projects based on the best available evidence to prevent unintended consequences.