Eversource Energy Faces Impairment Charges in Q4 2023 Amid Offshore Wind Challenges

Credit: Ørsted

Energy has reported impairment charges in its fourth-quarter 2023 earnings, stemming from its interests in joint ventures with involved in the development of the South Fork, Revolution, and Sunrise wind farms in the .

The company anticipates an after-tax impairment charge ranging between $1.4 billion and $1.6 billion. This includes $800 million to $900 million across all three projects, along with an additional charge of up to $700 million for Sunrise after local regulators rejected a request for higher rates.

See also: Aspen Power Acquires 42MW of Solar Projects in Pennsylvania from Sunrise Energy

Eversource's Chairman, President, and CEO, Joe Nolan, attributed the impairment to ongoing challenges in the offshore wind sector, citing supply chain disruptions and inflationary pressures. Nolan remarked, “Offshore wind projects continue to experience major supply chain disruption and inflationary challenges in the early stage of this growing industry in the US, and this impairment is an unfortunate reflection of the current market conditions we are facing.”

In response to these financial challenges, Eversource has entered into negotiations with a global private infrastructure investor for the potential sale of its ownership interest in the two joint ventures associated with the , Revolution Wind, and Sunrise Wind projects.

Nolan expressed appreciation for the collaboration with Orsted, stating, “We are pleased to advance the sale of our offshore wind interests and are appreciative of the support and collaboration we continue to receive from Orsted on this very complex transaction.”

See also: Eversource Energy Nears Deal to Offload 50% Stake in 1.8-GW US Offshore Wind Portfolio

The impairment was prompted by revised construction cost projections due to supply chain constraints affecting installation vessels and foundation fabrication. Eversource noted uncertainties related to the Sunrise Wind rebid process in New York, which further impacted the potential sales price.

The New York State Public Service Commission's denial of Sunrise Wind's petition to amend its OREC contract on October 12, 2023, also contributed to the challenges. Eversource is currently working with Orsted to evaluate the possibility of submitting a new bid for Sunrise Wind, considering the bid price and the likelihood of success in the new bidding process.

Add a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Keep Up to Date with the Most Important News

By pressing the Subscribe button, you confirm that you have read and are agreeing to our Privacy Policy and Terms of Use